Conway Village's Winter Commute Depends on One Week of Paving

The date on the Main Street project that matters most this fall is Oct. 15, not the end of November. That's when Alvin J. Coleman & Son plans to pave the stretch of Route 16 between Four Corners and the Saco River bridge. If the asphalt goes down, the traffic pattern from the Route 113 intersection to the bridge goes back to how it was before construction. If it doesn't, Conway Village goes into winter with the construction layout still in place.

Town Engineer Jim Badera, who manages the project, told selectmen it is on schedule. His concern is that paving might not happen before winter. "As we move forward in October and the temperature drops, our window for paving becomes narrow," he said. Nearly every decision about the project this month follows from that window, from how Fryeburg Fair week is handled to when the work stops.

What Is Torn Up Right Now

The official name is Conway 40638, the Main Street Eastern Project. It covers two intersections: Route 16 at Route 153, where Washington and Pleasant streets meet, and Route 16 at Route 113 in front of the Conway Public Library. The Department of Transportation is paying for the $6 million job. Construction started April 20, 2026. The town lists Oct. 1, 2027 as the completion date.

Phase 1 started at the Garg Complex across from the library. Its retaining wall came down so the road could be realigned. Phase 2 covers the stretch most people drive daily. Coleman laid temporary pavement on the east side of Route 16 from the Route 113 intersection north to the south end of the Saco River bridge. Both directions of traffic moved onto that side so crews could rebuild the west side.

The town's updates trace how the late-summer work led up to that shift:

  • On Aug. 8, ITG, the utility subcontractor for Consolidated Communications/Fidium, finished moving underground lines in front of Conway Marketplace.
  • On Aug. 19, Spectrum finished moving its overhead lines for the whole project area.
  • Coleman finished Phase 2 drainage on the west side of Route 16, in front of Conway Marketplace.
  • Road construction on the west side was scheduled to start Sept. 2, running from Route 113 north to the bridge.
  • On Sept. 14, crews were removing pavement and cutting out the southbound lane at the south end of the bridge, with flaggers alternating northbound and southbound traffic in a single lane.

For anyone shopping at Conway Marketplace, the important detail is which driveway is open. Entrances close one at a time while crews work in front of each one. The closures change day to day, and the contractor posts signs showing which entrances are open.

Why Fair Week Got Work and Columbus Day Didn't

Under the original schedule, Coleman would have taken Fryeburg Fair week off, Oct. 4 through 11, along with Columbus Day on Oct. 12. The contractor asked to keep working straight through to get ready for paving on Oct. 15, with the goal of having the road stable before the winter shutdown. Badera said the change was big enough that he took it to selectmen instead of approving it himself.

The board split the request. During fair week, Coleman can clean up the area next to Eastern Slope Dental at 51 White Mountain Highway, just north of the Irving station, as long as the work stays out of the travel lanes. Columbus Day is off-limits. Selectmen's chair Steve Porter explained why:

"That one day, traffic-wise here, is a nightmare with no construction, and you can't give me enough guarantees that with them working it's not going to impede traffic. It's a nightmare as it is."

So the week before paving has to fit two limits at once. Fair traffic is heading east to Fryeburg through the same intersection being rebuilt, and the long holiday weekend brings its own peak. The crew gets the fair-week days it asked for, but only off the road. That leaves very little room before Oct. 15, at a point in the season when every colder night narrows the paving window further.

What the Finished Intersection Changes

Going straight through Four Corners toward Fryeburg will stop being a straight shot. When the project is done, drivers headed to Fryeburg will take a curved lane in front of the Conway Public Library park. A new right-turn lane will run from northbound Route 16 onto eastbound Route 113. Route 113 also gets a second lane in front of the library.

Change

Where

Status as of early October 2026

Road realignment, retaining wall removed

Garg Complex, across from the library

Phase 1 work

Right-turn lanes and widening toward the bridge

Four Corners north to the Irving station and the Saco River bridge

Phase 2, paving targeted for Oct. 15

Curved Route 16 alignment for Fryeburg-bound traffic

In front of the Conway Public Library park

Part of the finished design, due 2027

Right-turn lane at Pleasant Street

Route 16 at Route 153

Phase 4, partly started during Phases 1 and 2

Signal timing changes

Four Corners

Badera confirmed timing would be adjusted

Selectman Ryan Shepard raised the signal question at a board meeting, saying the current timing "ruffles some feathers of those who are in a hurry." Badera confirmed the timing would be changed to improve traffic flow. The town hasn't published a timing plan.

West of Four Corners, there's already a finished example. The earlier Western Main Street phase, from the railroad tracks to Four Corners, was finished years before this contract began. It rebuilt the road and sidewalks, replaced a water main, moved crosswalks under the lights, and increased LED fixtures from 25 to 75 watts. The Eastern Project is a separate contract with its own phase numbers, so "Phase 1" this year refers to different work than it did in the Western phase.

The Side Streets Question Isn't Settled

The plan keeps two-way traffic on Route 16 for the whole job and doesn't send drivers onto nearby streets. Two Pollard Street residents still asked selectmen for temporary speed humps on Pollard and Chase streets during construction, to be removed in winter, to slow cut-through drivers. Badera recommended waiting. He noted that the 2026 work isn't near Pollard Street and that the town would have to pay for the humps. Porter disagreed. The Sept. 29 Select Board agenda includes a Main Street project discussion, but there's no separate item on speed humps, and no decision has been posted.

A Village Changing Alongside the Road

Not every change on Main Street this year is about the road. Stan's Service Center at 46 Main St. closed after more than 50 years. The business dates to Stan's Gulf in 1972, and its closing also ended Bellen's Service Center and Stan Anthony's Auto Sales. The Conway Daily Sun's coverage gave the reasons as small shops' growing difficulty servicing computer-dependent vehicles and uncertainty around inspections, not the road project. No sale or new use for the site has been announced.

The library at the center of the new alignment has a full October schedule. Its book sale runs Oct. 3 through 25. Tuesday Tales meets Oct. 6 from 10:30 to 11:30 a.m., and the VEX Robotics & 3D Printing Club meets Oct. 8 from 3:30 to 4:30 p.m. The book sale's three weeks overlap Oct. 15, so anyone browsing it may see the Four Corners paving happen in person.

After November

Construction is set to continue through November, stop for the winter, start again in April 2027, and finish in October 2027. Badera said he would update the Town Engineer page every two weeks and brief selectmen at their meetings. The latest posted traffic alert is dated Sept. 14, so the next update should say whether the Oct. 15 paving happened. Questions, comments, and complaints go to [email protected], and Badera has committed to answering them promptly.

Pinkham Real Estate works out of North Conway, just up Route 16 from Four Corners, and we follow projects like this one because they affect how people get around the Valley every day. If you'd like to talk through how the finished Four Corners might change your daily routes, contact our team to start your Mount Washington Valley search.

Work With Us

Your key to real estate success lies with The Pinkham team! Our skilled and diverse group of professionals, licensed in both NH and Maine, work in perfect harmony. With a strong emphasis on communication, collaboration, and continuous learning, we strive to surpass expectations. Partner with us today and unlock the true potential of your property endeavors.

CONTACT US